Castro Valley, CA · 2026
4,760 SF demolished · 4 in asphalt
20519 Wisteria Street
An apartment alley rebuilt from the base up: old pavement removed, a 140 LF concrete valley gutter poured, and 4,340 SF of new asphalt placed and sealed.
General Contractors · Dublin, CA
The 1.5 in final surface course over 50,270 SF of parking lot on a new building, placed once construction traffic was gone, around fresh curbs, planters and utility boxes.
On a new building, the parking lot is usually paved in two stages. A first lift of base asphalt goes down early, and the site runs on it while the building goes up. Heavy equipment and deliveries scar that first lift, so the finish layer waits until construction traffic is done. Here the base lift was already in place when we arrived, and our job was the final surface course.
By then the curbs, planters, sidewalks and utility boxes were all set, so the new asphalt had to meet fixed edges rather than set its own. The utility boxes sat high and parts of the perimeter needed more material than the original quantity covered, so a change order added 23 tons of asphalt to give a 6-inch curb reveal instead of leaving the edges short.
Tack coat (SS-1h, about 440 gallons) went down on the base lift ahead of the paver, then the 1.5 in surface course of 1/2 in hot mix followed. The paving train was a paver, two rollers and two skid steers with a sweeper, with trucks bringing mix from the plant: 27 loads over the job.
The estimated crew was ten: a foreman, six operators, a laborer, a driver/operator and a superintendent, scheduled for two weekdays.
The parking lot got its finished 1.5 in surface course across the full 50,270 SF, with the extra material the edges and utility boxes needed handled by change order rather than left short.
On site
More work
Castro Valley, CA · 2026
4,760 SF demolished · 4 in asphalt
An apartment alley rebuilt from the base up: old pavement removed, a 140 LF concrete valley gutter poured, and 4,340 SF of new asphalt placed and sealed.
Alameda, CA · 2025
18,390 SF sealed
A school yard sealed in two coats and re-striped for play: four-square, hopscotch, volleyball and basketball lines, plus painted playground games.
Hayward, CA · 2020
2,300 tons of asphalt removed and replaced
A school site with soft subgrade found during demolition, treated with cement and lime and regraded before the new asphalt went down.
Get started
Send the address and what you are seeing. An estimator will walk it and tell you what is actually failing before quoting anything.