The challenge
On a new building, the parking lot is usually paved in two stages. A first lift of base asphalt goes down early, and the site runs on it while the building goes up. Heavy equipment and deliveries scar that first lift, so the finish layer waits until construction traffic is done. Here the base lift was already in place when we arrived, and our job was the final surface course.
By then the curbs, planters, sidewalks and utility boxes were all set, so the new asphalt had to meet fixed edges rather than set its own. We found an elevation issue: the utility boxes sat high, and parts of the perimeter needed more material than the original quantity covered. We brought it to the general contractor and recommended adding 23 tons of asphalt to build the edges up to a 6-inch curb reveal. Everyone agreed, and the adjustment prevented a drainage problem along the edges of the new lot.
How it was executed
Tack coat (SS-1h, about 440 gallons) went down on the base lift ahead of the paver, then the 1.5 in surface course of 1/2 in hot mix followed. The paving train was a paver, two rollers and two skid steers with a sweeper, with trucks bringing mix from the plant: 27 loads over the job.
The crew was ten: a foreman, six operators, a laborer, a driver/operator and a superintendent, over two weekdays.
The result
The parking lot got its finished 1.5 in surface course across the full 50,270 SF, with the edges built up around the high utility boxes so the lot drains the way it should.