Working in the downtown right-of-way
Downtown Oakland streets are public right-of-way, busy with traffic, transit, deliveries and pedestrians. Work there falls under City of Oakland Department of Transportation requirements, and closing several streets at once isn't an option.
At 226 13th Street, the Lydian Apartments development covering a full city block, we ground and repaved four city streets totaling 35,350 SF to 2 inches and remarked them with thermoplastic in four days. The key was keeping public access open at every stage while meeting the City's requirements.
The general contractor's project manager credited our phasing plan with making the job work. That's typical downtown: the paving is straightforward, and the planning is the hard part.